KIPIC has successfully installed all the units in package 3

18 Jun 19




KIPIC has successfully installed all the units in package 3

KIPIC has successfully installed all the units in package 3 . Module 6000BP01M is the heaviest modules in package 3 (Utilities) among 51 modules, this module is a portion of Unit 60 steam generation well known as the Boiler with a weight of 880 Tone. One of the greatest challenges is achieved after intense logistics planning and effective site preparation that lead to success of transporting module 6000BP01M to its final location at site safely.


KIPIC was launched on May 1st 2017 and is responsible for operating and managing refining, liquefied natural gas, and petrochemicals activities of Al-Zour complex. This consists of a total of six Al-Zour locations